Hands-on: Optimize 24-Hour Dispatch

🚀 Module 5: Dispatch & Optimization

Hands-on: Optimize 24-Hour Dispatch

In this hands-on exercise, you will design and execute a 24-hour battery dispatch schedule that maximizes revenue while respecting operational constraints.

Exercise Overview

You are given a 50 MW / 200 MWh lithium-ion battery system (4-hour duration) connected to a grid node with the following characteristics:

  • Round-trip efficiency: 88%
  • Maximum C-rate: 0.5C (25 MW charge, 50 MW discharge -- asymmetric)
  • SOC operating window: 10% - 90% (160 MWh usable)
  • Degradation cost: $35/MWh throughput
  • Initial SOC: 50%

Price Forecast

The day-ahead price forecast for the 24-hour period:

Hour 00-03:  $22/MWh  (overnight valley)
Hour 04-06:  $28/MWh  (early morning)
Hour 07-09:  $45/MWh  (morning ramp)
Hour 10-13:  $18/MWh  (solar surplus -- negative net load)
Hour 14-16:  $38/MWh  (afternoon)
Hour 17-19:  $92/MWh  (evening peak -- solar cliff)
Hour 20-22:  $55/MWh  (evening decline)
Hour 23:     $30/MWh  (approaching overnight)

Tasks

  1. Calculate the optimal dispatch schedule. Determine the charge/discharge power for each hour that maximizes net revenue (energy revenue minus degradation cost minus charging cost). Use the dashboard's dispatch planning tool or calculate manually.
  1. Identify the best arbitrage windows. Which hours should the battery charge? Which should it discharge? Calculate the expected gross and net revenue for your schedule.
  1. Check SOC feasibility. Trace the SOC trajectory through the 24 hours. Verify that SOC stays within 10-90% at all times and that the battery has sufficient energy stored before the evening peak discharge window.
  1. Handle a real-time deviation. At hour 14, the actual real-time price jumps to $75/MWh (instead of the forecasted $38/MWh) due to an unexpected generator trip. Should you deviate from the day-ahead schedule? If so, how much should you discharge?
  1. Add frequency regulation. Reserve 10 MW of the battery's capacity for frequency regulation, which pays $25/MW-hour. Recalculate the optimal arbitrage schedule with only 40 MW available for arbitrage. Compare total revenue.
  1. Sensitivity analysis. How does revenue change if round-trip efficiency drops to 82%? If degradation cost increases to $50/MWh? If the evening peak price is only $65/MWh instead of $92/MWh?

What You Will Learn

  • Practical dispatch optimization for a real price profile
  • The trade-off between arbitrage depth and degradation cost
  • Revenue stacking (arbitrage + ancillary services)
  • Handling real-time forecast deviations
  • Sensitivity to key economic parameters

This exercise uses the Grid Simulator. Click the Launch button below to open the Dispatch Optimizer lab. The tool includes a visual SOC trajectory chart and a revenue calculator.