Hands-on30 min
Hands-on: Optimize 24-Hour Dispatch
🚀 Module 5: Dispatch & Optimization
Hands-on: Optimize 24-Hour Dispatch
In this hands-on exercise, you will design and execute a 24-hour battery dispatch schedule that maximizes revenue while respecting operational constraints.
Exercise Overview
You are given a 50 MW / 200 MWh lithium-ion battery system (4-hour duration) connected to a grid node with the following characteristics:
- Round-trip efficiency: 88%
- Maximum C-rate: 0.5C (25 MW charge, 50 MW discharge -- asymmetric)
- SOC operating window: 10% - 90% (160 MWh usable)
- Degradation cost: $35/MWh throughput
- Initial SOC: 50%
Price Forecast
The day-ahead price forecast for the 24-hour period:
Hour 00-03: $22/MWh (overnight valley)
Hour 04-06: $28/MWh (early morning)
Hour 07-09: $45/MWh (morning ramp)
Hour 10-13: $18/MWh (solar surplus -- negative net load)
Hour 14-16: $38/MWh (afternoon)
Hour 17-19: $92/MWh (evening peak -- solar cliff)
Hour 20-22: $55/MWh (evening decline)
Hour 23: $30/MWh (approaching overnight)Tasks
- Calculate the optimal dispatch schedule. Determine the charge/discharge power for each hour that maximizes net revenue (energy revenue minus degradation cost minus charging cost). Use the dashboard's dispatch planning tool or calculate manually.
- Identify the best arbitrage windows. Which hours should the battery charge? Which should it discharge? Calculate the expected gross and net revenue for your schedule.
- Check SOC feasibility. Trace the SOC trajectory through the 24 hours. Verify that SOC stays within 10-90% at all times and that the battery has sufficient energy stored before the evening peak discharge window.
- Handle a real-time deviation. At hour 14, the actual real-time price jumps to $75/MWh (instead of the forecasted $38/MWh) due to an unexpected generator trip. Should you deviate from the day-ahead schedule? If so, how much should you discharge?
- Add frequency regulation. Reserve 10 MW of the battery's capacity for frequency regulation, which pays $25/MW-hour. Recalculate the optimal arbitrage schedule with only 40 MW available for arbitrage. Compare total revenue.
- Sensitivity analysis. How does revenue change if round-trip efficiency drops to 82%? If degradation cost increases to $50/MWh? If the evening peak price is only $65/MWh instead of $92/MWh?
What You Will Learn
- Practical dispatch optimization for a real price profile
- The trade-off between arbitrage depth and degradation cost
- Revenue stacking (arbitrage + ancillary services)
- Handling real-time forecast deviations
- Sensitivity to key economic parameters
This exercise uses the Grid Simulator. Click the Launch button below to open the Dispatch Optimizer lab. The tool includes a visual SOC trajectory chart and a revenue calculator.
Open Hands-on Lab
Complete the exercise in the live dashboard.
Log in to track your progress and earn certifications.