The FDE 30-Day Playbook: Day 0 to Customer Go-Live
🎯 Module 10: The FDE Career — From Course to Khazna
The FDE 30-Day Playbook: Day 0 to Customer Go-Live
Every FDE deployment follows the same pattern. It does not matter if you are deploying at a Khazna data center in Abu Dhabi or a TAQA substation in Fujairah. The playbook is the same.
Here is exactly what happens in your first 30 days on a customer site.
Phase 0: Site Survey (Day 0-3)
Before you touch a single device, you survey.
- Device inventory: Walk every room. List every meter, BESS, HVAC, EV charger. Note the make, model, and firmware version.
- Network topology: Draw the network. Where are the Modbus gateways? What is the IP range? Is there a DMZ between OT and IT?
- Protocol check: Which devices speak Modbus TCP? Which speak BACnet/IP? Any legacy DNP3 or IEC 104?
Deliverable: Site survey document (device list + network diagram + protocol map)Phase 1: Protocol Configuration (Day 4-10)
Now you connect. This is where the 7 primitives come in.
- Modbus devices: Map register addresses. Configure polling intervals. Test reads.
- BACnet objects: Discover object IDs. Set up COV (Change of Value) subscriptions.
- OCPP connectors: Register charge points. Configure connector IDs and meter values.
- Test every connection: Run
GET /api/v1/sites/{id}/assetsand verify every device shows "connected."
# Verify all devices are reporting
curl -H "Authorization: eat_live_xxx" \
https://app.energyatit.com/api/v1/assets?site_id=42# Verify all devices are reporting
curl.exe -H "Authorization: eat_live_xxx" "https://app.energyatit.com/api/v1/assets?site_id=42"Phase 2: Test & Validate (Day 11-20)
This is where you prove the system works.
- Test dispatches: Send charge/discharge commands to every BESS. Verify read-back.
- First carbon attestation: Create your first hash-chained carbon record from live meter data.
- Compliance dry run: Generate an IEC 61850 or GHG Scope 2 compliance package. Review gaps.
- Alarm testing: Trigger edge cases. What happens when a device goes offline? Does the alert fire?
Phase 3: Go-Live (Day 21-30)
This is the handover. You are shipping a production system.
- Production API keys: Generate
eat_live_keys for the customer's systems - Monitoring dashboards: Set up real-time views for operations teams
- Customer training: Walk the ops team through the dashboard, dispatch controls, and compliance reports
- Handover documentation: Write the runbook — what to do when things break
Deliverable: Signed go-live checklist + customer training completion30 days. That is all it takes to go from an empty site to a fully deployed energy management system. That is the power of platform-based deployment.