The FDE 30-Day Playbook: Day 0 to Customer Go-Live

🎯 Module 10: The FDE Career — From Course to Khazna

The FDE 30-Day Playbook: Day 0 to Customer Go-Live

Every FDE deployment follows the same pattern. It does not matter if you are deploying at a Khazna data center in Abu Dhabi or a TAQA substation in Fujairah. The playbook is the same.

Here is exactly what happens in your first 30 days on a customer site.

Phase 0: Site Survey (Day 0-3)

Before you touch a single device, you survey.

  • Device inventory: Walk every room. List every meter, BESS, HVAC, EV charger. Note the make, model, and firmware version.
  • Network topology: Draw the network. Where are the Modbus gateways? What is the IP range? Is there a DMZ between OT and IT?
  • Protocol check: Which devices speak Modbus TCP? Which speak BACnet/IP? Any legacy DNP3 or IEC 104?
Deliverable: Site survey document (device list + network diagram + protocol map)

Phase 1: Protocol Configuration (Day 4-10)

Now you connect. This is where the 7 primitives come in.

  • Modbus devices: Map register addresses. Configure polling intervals. Test reads.
  • BACnet objects: Discover object IDs. Set up COV (Change of Value) subscriptions.
  • OCPP connectors: Register charge points. Configure connector IDs and meter values.
  • Test every connection: Run GET /api/v1/sites/{id}/assets and verify every device shows "connected."
# Verify all devices are reporting
curl -H "Authorization: eat_live_xxx" \
  https://app.energyatit.com/api/v1/assets?site_id=42
# Verify all devices are reporting
curl.exe -H "Authorization: eat_live_xxx" "https://app.energyatit.com/api/v1/assets?site_id=42"

Phase 2: Test & Validate (Day 11-20)

This is where you prove the system works.

  • Test dispatches: Send charge/discharge commands to every BESS. Verify read-back.
  • First carbon attestation: Create your first hash-chained carbon record from live meter data.
  • Compliance dry run: Generate an IEC 61850 or GHG Scope 2 compliance package. Review gaps.
  • Alarm testing: Trigger edge cases. What happens when a device goes offline? Does the alert fire?

Phase 3: Go-Live (Day 21-30)

This is the handover. You are shipping a production system.

  • Production API keys: Generate eat_live_ keys for the customer's systems
  • Monitoring dashboards: Set up real-time views for operations teams
  • Customer training: Walk the ops team through the dashboard, dispatch controls, and compliance reports
  • Handover documentation: Write the runbook — what to do when things break
Deliverable: Signed go-live checklist + customer training completion

30 days. That is all it takes to go from an empty site to a fully deployed energy management system. That is the power of platform-based deployment.