Hands-on: SSH Into a Substation

⚡ Module 1: Power Grid 101

Hands-on: SSH Into a Substation

In this hands-on exercise, you will connect to a simulated substation environment and explore its telemetry data, control interfaces, and protocol endpoints.

Exercise Overview

You will use the EnergyAtIt live dashboard to interact with a simulated 132/33 kV substation. The substation model includes:

  • Two power transformers (60 MVA each) with on-load tap changers
  • Six outgoing 33 kV feeders with motorized circuit breakers
  • Bus section breaker for split-bus operation
  • Protection relays (overcurrent, distance, differential)
  • Revenue meters on each feeder

Tasks

  1. Explore the telemetry tree. Navigate the substation's data model in the dashboard. Identify the bus voltage, feeder currents, and transformer loading for each phase. Note how values are organized hierarchically: Substation > Voltage Level > Bay > Device > Data Point.
  1. Read IEC 61850 data objects. Using the protocol inspector panel, observe the MMS data structure:
  • Logical Device: SUB1_LD0
  • Logical Nodes: XCBR1 (circuit breaker), MMXU1 (measurement), PTOC1 (overcurrent protection)
  • Data Objects: MMXU1.TotW (total watts), MMXU1.TotVAr (total VARs), XCBR1.Pos (breaker position)
  1. Monitor a tap change operation. Observe the transformer tap position changing as the automatic voltage regulator (AVR) adjusts to maintain the 33 kV bus within +/- 5% of nominal. Watch how ATCC1.TapPos increments and the bus voltage responds.
  1. Trigger a breaker trip. Using the control panel, simulate a fault on Feeder 3. Observe the protection relay (PTOC1) picking up within 50 ms and the circuit breaker (XCBR1) opening within 80 ms. Note the sequence-of-events log with millisecond timestamps.
  1. Export telemetry as CSV. Download 15 minutes of 1-second resolution data for the main bus and verify the data quality: no gaps, consistent timestamps, values within expected ranges.

What You Will Learn

  • How substation telemetry is organized in a hierarchical data model
  • The relationship between IEC 61850 logical nodes and physical devices
  • How protection operates in real time (pickup, trip, reclose sequences)
  • Data quality characteristics of substation SCADA

This exercise uses the Grid Simulator. Click the Launch button below to open the Substation Explorer lab.

Open Hands-on Lab

Complete the exercise in the live dashboard.

Launch