Final Project: Full Grid Operator
🌱 Module 6: Carbon & Compliance
Final Project: Full Grid Operator
In this capstone project, you will operate a complete grid simulation that combines everything you have learned across all six modules: grid fundamentals, industrial protocols, telemetry monitoring, grid operations, dispatch optimization, and carbon compliance.
Project Overview
You are the grid operator for a 2 GW interconnected system serving a mixed urban, industrial, and commercial load. The simulation runs for a 48-hour period (compressed to 60 minutes real time) and includes:
Generation Assets:
- 2 x 300 MW combined-cycle gas turbines (Modbus TCP telemetry)
- 1 x 200 MW solar farm with cloud variability (SunSpec Modbus)
- 1 x 100 MW wind farm with forecast uncertainty
- 3 x 50 MW / 200 MWh battery systems (Modbus TCP control)
Load Centers:
- 1 x 80 MW data center with BACnet cooling systems and SNMP-monitored IT equipment
- 500 EV chargers across 10 stations (OCPP 2.0)
- 800 MW of residential/commercial load with temperature-dependent demand
- 200 MW of industrial load with interruptible contracts
Network:
- 4 substations with IEC 61850 telemetry
- 132 kV transmission ring with thermal constraints
- 33 kV distribution with voltage regulation
Tasks
- Day-ahead planning. Given weather forecasts and load projections, create a generation dispatch schedule and battery charge/discharge plan. Maximize renewable utilization while maintaining reserves.
- Real-time operations. Monitor the grid through the NOC dashboard. Respond to events as they occur: solar ramps, load surges, equipment trips, and frequency excursions. Use all available resources: gas turbine ramping, battery dispatch, EV curtailment, and industrial DR.
- Demand response event. At hour 18 (simulated), a DR event is issued via OpenADR requiring 150 MW of load reduction for 2 hours. Orchestrate the response across EV chargers (OCPP SetChargingProfile), data center cooling (BACnet), and industrial loads (Modbus).
- Carbon tracking. Throughout the simulation, maintain real-time carbon intensity tracking. Use hash-chained attestation for all carbon records. Generate a 48-hour carbon report broken down by source, scope, and hour.
- Compliance reporting. At the end of the simulation, generate reports for DEWA (DSM performance), FERC 2222 (DER aggregation performance), and EU EED (data center energy metrics including PUE and renewable share).
Scoring Criteria
- Reliability: Frequency within +/- 0.1 Hz for > 99% of time; no voltage violations
- Economics: Total cost of operations (fuel + degradation + DR payments)
- Carbon: Total emissions and carbon intensity (gCO2/kWh)
- Renewable utilization: % of available renewable energy captured (target: > 95%)
- DR performance: Response speed and accuracy vs. baseline
- Compliance: Completeness and accuracy of generated reports
- Data quality: Telemetry completeness > 99%, all carbon records pass chain verification
This exercise uses the Grid Simulator. Click the Launch button below to open the Grid Operator Capstone lab. Allow 60 minutes for the full exercise.
Open Project
Complete the exercise in the live dashboard.
Log in to track your progress and earn certifications.